Who issues the permit and how inspections work
In Chino, building permits come from the city's Building Division, and its rule is broad, covering all work except what the California codes carve out. When your job needs a permit, we settle with you who pulls it before anything starts. If it's not clear whether it needs one, we check with the division first instead of guessing.
A permit changes the schedule more than the pour does, because the job stops at each inspection until the inspector signs off. Inspectors come out to check the work against the codes, and the city asks callers to phone in before 3 pm for a next-day visit. We plan forming and pouring around those visits so a truck of concrete isn't waiting on a sign-off.
- Forms, base and steel are ready before the inspector arrives.
- Your schedule counts inspection days, not just pour day.
- If you pull the permit yourself, we work to its inspections.